Construction progress

фото 9 Alter Ego Коммерческая недвижимость
22.09.2017

As at 22th September 2017, the following construction works were carried out at Alter Ego premium class residential complex (7 Laboratornyi Lane, Kyiv):

 

Residential block A:

  • brick laying works (internal walls) – 79% complete
  • windows installation – 99% complete
  • flooring works in apartments and public areas at the level of 16th-21th floors
  • balconies protective structures installation – 65% complete

 

Residential block B:

  • brick laying works (internal walls) – 80% complete
  • windows installation – 97% complete

 

At the site:

  • external water supply system installation – 95% complete
  • external power supply system installation – 80% complete
  • insulation works in the parking – 85% complete

 

Alter Ego residential complex comprises two 24-storey residential blocks. The total area of the complex is 43.6 thousand sq m. Areas of the 360 apartments vary from 52 to 170 sq m.

 

The internal infrastructure of the complex will include a fitness center, restaurant, shops, and other amenities.

 

We are glad to answer all your questions and assist with selection of an apartment or an office!

 

+38 (044) 290 30 82

market@tmm.ua

Провулок Лабораторний, 7

http://pechersk.tmm.ua

https://www.facebook.com/alter.ego.tmm/

https://www.youtube.com/channel/UCLB3mSwSIFteqVWYsmm9HhQ

 

фото 10 Alter Ego Коммерческая недвижимость, фото 10 Alter Ego Коммерческая недвижимость, фото 10 Alter Ego Коммерческая недвижимость
19.07.2017

As at 19th July 2017, the following construction works were carried out at Alter Ego premium class residential complex (7 Laboratornyi Lane, Kyiv):

Residential block A:

·         brick laying works (internal walls) – 40% complete

·         windows installation – 95% complete

·         flooring works in apartments and public areas at the level of 11th-12th floors

·         balconies protective structures installation – 30% complete

·         ventilated facade works – 55% complete

Residential block B:

·         brick laying works (internal walls) – 40% complete

·         translucent protective structures installation – 40% complete

·         windows installation – 85% complete

At the site:

·         external water supply system installation – 90% complete

·         external power supply system installation – 55% complete

·         insulation works in the parking – 10% complete

 

Alter Ego residential complex comprises two 24-storey residential blocks. The total area of the complex is 43.6 thousand sq m. Areas of the 360 apartments vary from 52 to 170 sq m.

 The internal infrastructure of the complex will include a fitness center, restaurant, shops, and other amenities.

 We are glad to answer all your questions and assist with selection of an apartment or an office!

 

+38 (044) 490 22 22
market@tmm.ua
7 Laboratornyi Lane, Kyiv
http://pechersk.tmm.ua