Construction progress

фото 7 Alter Ego Коммерческая недвижимость
28.12.2017

As at 29 December 2017, the following construction works were carried out at Alter Ego premium class residential complex:

Residential block А:

  • brick laying works (internal walls) – 99%
  • facade works – 92%
  • flooring works in apartments and public areas at the level of – 23rd  floor
  • doors assembly and installation – 65%
  • balconies protective structures installation – 92%
  • finishing works – 34%

Residential block B:

  • brick laying works (internal walls) – 90%
  • doors installation – 45%
  • balconies protective structures installation – 72%

 Parking:

  • parking lot flooring – 96%
  • ventilation, smoke removal, firefighting systems – 55%

At the site:

  • external water supply system – 99%
  • external power supply and lighting systems – 94%
  • external sewerage system – 60%

Alter Ego residential complex comprises two 24-storey residential blocks. Areas of the 360 apartments with modern layout solutions vary from 52 sq. m to 268 sq. m.

The internal infrastructure of the complex will include a parking lot, fitness center, restaurant, shops, and other amenities for comfortable living of the residents.

We are glad to answer all your questions and assist with selection of an apartment or an office!

+38 (044) 290 30 82

market@tmm.ua

7 Laboratornyi Lane, Kyiv

http://pechersk.tmm.ua

https://www.facebook.com/alter.ego.tmm/

https://www.youtube.com/channel/UCLB3mSwSIFteqVWYsmm9HhQ

 

фото 8 Alter Ego Коммерческая недвижимость, фото 8 Alter Ego Коммерческая недвижимость, фото 8 Alter Ego Коммерческая недвижимость
01.11.2017

As at 31 October 2017, the following construction works were carried out at Alter Ego premium class residential complex:

Residential block А:

  • brick laying works (internal walls) – 95%
  • windows installation – 99%
  • facade works – 85%
  • flooring works in apartments and public areas at the level of – 22nd -23rd  floors
  • doors assembly and installation – 45%
  • balconies protective structures installation – 85%
  • finishing works – 25%

Residential block B:

  • brick laying works (internal walls) – 80%
  • translucent protective structures installation – 99%
  • doors installation – 20%
  • balconies protective structures installation – 55%

 Parking:

  • parking lot flooring – 92%
  • ventilation, smoke removal, firefighting systems – 45%
  • insulation works – 100%

At the site:

  • external water supply system – 99%
  • external power supply and lighting systems – 87%
  • external sewerage system – 45%

Alter Ego residential complex comprises two 24-storey residential blocks. Areas of the 360 apartments with modern layout solutions vary from 52 sq. m to 268 sq. m.

The internal infrastructure of the complex will include a parking lot, fitness center, restaurant, shops, and other amenities for comfortable living of the residents.

We are glad to answer all your questions and assist with selection of an apartment or an office!

+38 (044) 290 30 82

market@tmm.ua

7 Laboratornyi Lane, Kyiv

http://pechersk.tmm.ua

https://www.facebook.com/alter.ego.tmm/

https://www.youtube.com/channel/UCLB3mSwSIFteqVWYsmm9HhQ