As at 12th April 2017, the following construction works were carried out at Alter Ego premium class residential complex (7 Laboratornyi Lane, Kyiv):

Residential block A:

- monolithic frame construction (vertical) at the level of 26th floor

- horizontal slabs construction at the level of 25th-26th floors

- ventilation and fire alarm systems installation at 18th floor

- brick laying works (internal walls) up to 16th floor

- double glazed windows installation at the level of 19th floor

- aluminum window elements installation up to 14th floor

- elevator equipment installation (Orona) – 2 units

- flooring underlayment in apartments and common areas

Residential block B:

- monolithic frame construction (vertical) at the level of 24th-25th floors

- horizontal slabs construction at the level of 24th-25th floors

- interior stairs construction

- brick laying works (internal walls) up to 14th floor

- ventilation system installation at 14th floor

- parking floors insulation works

 